It’s all about extremes on this track: high speeds, sharp turns, steep slopes that push tires and vehicles to their limits.
Testing the limits on the road
ÖAMTC EXPERIENCE CENTER
Testing the limits on the road
ÖAMTC EXPERIENCE CENTER
Since we were using asphalt, we leased ecological compensation areas and created special biotopes without fencing as well as a 700 m guidance system for amphibians. Manfred Pfeiffenberger, Head of the Center: “We wanted to build the center – but not at all costs.”
Before the start of construction, Felix Brennsteiner (markand GmbH) developed a detailed 3D model of the track with all turns, slopes and the 180 watering points. The construction company used the model as a guidance for implementing the plans.
A 2,000 cubic meter utility water basin supplies the racetrack’s water cycle. Excess water (e.g. caused by rainfall) is filtered and drained on the grounds.
The narrow slot channel on the red and white curb offers an even surface in support of vehicle traction.
It’s all about extremes on this track: high speeds, sharp turns, steep slopes that push tires and vehicles to their limits.
Since we were using asphalt, we leased ecological compensation areas and created special biotopes without fencing as well as a 700 m guidance system for amphibians. Manfred Pfeiffenberger, Head of the Center: “We wanted to build the center – but not at all costs.”
Before the start of construction, Felix Brennsteiner (markand GmbH) developed a detailed 3D model of the track with all turns, slopes and the 180 watering points. The construction company used the model as a guidance for implementing the plans.
A 2,000 cubic meter utility water basin supplies the racetrack’s water cycle. Excess water (e.g. caused by rainfall) is filtered and drained on the grounds.
How about range tests for electric vehicles or for innovations from the automotive?
We wanted to build the center – but not at all costs.
The narrow channel is an excellent solution for draining water from the track.
They were flexible and able to supply special heights for the individual elements. BG-Graspointner’s hydraulic calculations were another bonus point. This helped us to plan even more strategically. It was great working with them, and we would be happy to do so again in the future.
Project overview
Project name
ÖAMTC Experience Center
Location
Saalfelden, Austria
Installed channel types
BG-FILCOTEN® light, NW 150 Slot top D400
Total installed length in meters
525 m
Services BG-Support
Hydraulic calculations, planning radially installed slot tops
Client/builder
ÖAMTC Saalfelden
BG-Project team:
Kirchebner; Unterberger
Planer
markand GmbH; Wurz Design
Building contractor
Swietelsky, Zell am See
Markus Unterberger
Technical Support
BG-Graspointner | Austria